Construction Updates

Scheduled work
IMPORTANT NOTE: Dates for all outdoor projects are weather dependent. For your safety and the safety of the crews working, please be patient, follow flag person directions and obey all signs in the area. We appreciate your patience and understanding. 


Contacts:
Parks and Open Spaces
Roads
Water and Wastewater

TimelineLocationDescriptionDept
Aug 2019-Aug 2020
Greystone development (former Burnco site east of River Ave, between the Bow River and Griffin Rd)
Reclamation work required to make gravel pit land fit for development (provincially regulated process).
Greystone
July 8-28 (rescheduled)

River Heights Dr between Willow Gate and Willow DrRiver Heights Dr between Willow Gate and Willow Dr is closed for third-party utility tie-ins.Kira Golden, North Star Contracting, 403-228-3421
Summer 2019 (until further notice)

Town pathways

Various pathway closures due to weather impacts and erosion. Repairs being made in priority order.

The bridge in Riverview is damaged structurally and is closed until repairs or replacement are done. Please see map for detour.
Parks and Open Spaces
Aug 2019-Apr 2020West of Hwy 22 from north of Hwy 1A to south of the Bow RiverTC Energy pipeline work. Details and maps to come.

Contacts:
westpathdelivery@transcanada.com
1-844-551-0054
Project website

June-JulyNE of Hwy 1A/22 intersectionHistorical resources investigations
Archaeological excavations are scheduled near the Hwy 1A/22 interchange project, including archaeological hand excavations at four locations northeast of the intersection.
Alberta Transportation
May-JuneSW corner of the northern portion of Highway 22 dog park near Westrock Rd

Starting May 22, a portion of the Highway 22 dog park will be closed due to construction in the area.

Construction is anticipated to continue for 6-8 weeks.Please watch for personnel and equipment, obey signage and use caution while in the area.

View the map here.
Parks and Open Spaces
July-Aug 2019 George Fox Trail

Griffin Road

James Walker Trail
George Fox Trail upgrading
- July-Sept 2019
- 2km of road resurfacing
- road markings
- bikes lanes
- new regional pathway connections

Griffin Road
- Aug-Sept 2019
- approx 2km of arterial roadway top   lift paving  

James Walker Trail extension
- Summer 2019-Fall 2020
- 1.5km of new arterial roadway connection from new Bridge to Riviera, incl. 3 roundabouts and regional pathway connections

Roads
Summer 2019Horse Creek Road Pedestrian CrossingThe Town and CP are collectively working on the design of this crossing. Additional scope has been added to relocate some siding track that conflicts with the alignment of the crossing location. This conflict has a large impact on the safety of the crossing and CP is currently preparing a work plan to relocate the track. This crossing is a priority and will continue to be advanced in a timely way. Early indication from CP is that the project implementation will now be delayed until the spring of 2019 while design details are finalized.Roads
Summer 2018-Fall 2020Jack Tennant Memorial Bridge across the Bow RiverThe new bridge across the Bow River near SLS Family Sports Center. The new bridge and arterial road connections also include on-street bike lanes and a separated, parallel 3-metre wide multi-use pathway that connects with Cochrane’s existing pathway system.

Steel girders begin to arrive Apr 15: watch for oversized loads coming from the south along Hwy 22, then east on Griffin Rd to the construction site. Expect delays; please give trucks room to maneuver and obey flaggers.

More: cochrane.ca/Bridge
TBC

Hwy 1A/22 interchange

The 2017 provincial budget included funding to begin the process for building an interchange at Highway 1A and 22. Once design and engineering are complete, construction could begin as early as fall 2019, and is expected to take about two years to complete. (A more detailed project timeline will be available once the design process is complete.)